Re-development of Lesmurdie Primary School

Exciting times ahead

Latest Update - August 2022

Teaching Block 1 (TB1) -  kitchen cabinetry installed, painting near complete

Teaching Block 2 (TB2) - roof work complete

Covered assembly - vertical cladding

Transportables - ordered

 

Scheduled works in the coming months:

Teaching Block 1 (TB1) -  commence internal flooring, splash back and wet area tiling, install lights and switches

Teaching Block 2 (TB2)- complete joinery and cabinetry, paving and painting

Covered assembly - brick cleaning, commence tiling to canteen

Site works - prep limetone and commence paving to areas around TB2 and covered assembly,

install shade structure steel

 

 

Lesmurdie Primary School is going through an exciting transformation. From October 2021 to November 2023 we are replacing our outdated buildings with modern, purpose-built facilities.

The new facilities will provide our students with an ideal learning environment, offering them a great start to life. The redevelopment will benefit current and future generations of Lesmurdie children.

Alot of the progress is now being made inside the buildings - painting, tiling and cabinetry work all happening at the moment.

New Design

The school has a new design to fit our local environment and best meet the needs of our students, teachers and community.

Our buildings will open onto a central lawned area, providing the children with a safe and inclusive space to play and learn.

The children will continue to have access to nature play areas and enjoy views of the bush reserve.

Our younger students will have a dedicated early childhood learning area – the perfect environment to start their education.

We will also have access to a new shared-use oval on Ray Owen Reserve.

Facilities

Stage 1 (October 2021 – September 2022):

  • Two teaching blocks for our early childhood and junior students
  • Purpose-built early childhood play area
  • Covered Assembly area
  • Hardcourts

Stage 2 (December 2022 – November 2023):

  • Administration block
  • Dental Therapy centre (currently located at Walliston PS)
  • Teaching Block for our senior students
  • Staff room
  • Conference room
  • A central lawn area

The existing art and music rooms and library will remain.

Teaching & Learning

Plans are in place to maintain a safe learning environment and minimise disruption to teaching and learning.

  • Fences are in place to separate the children from the construction site.
  • The main entry points for contractors will be the staff carpark off Sanderson Street and an entry off Willoughby Road.
  • Temporary buildings will be provided as additional classrooms during Stage 2.
  • Demolition of the old buildings will take place during the 2022/23 summer school holidays by licenced professionals.

Dental Therapy

During the redevelopment Dental Therapy is operating out of Walliston Primary School.

Old School Site Established in 1920

Re-development lesmurdie primary school

First school 1920 - Private Residence
1 Wheelwright Road, Lesmurdie

Re-development lesmurdie primary school

Lesmurdie School
Old Site Sanderson Road 1921

Re-development lesmurdie primary school

Lesmurdie Primary School
Old site Sanderson Road

Re-development lesmurdie primary school

Later picture of old school site